Project overview

MKUH’s new Imaging Centre is replacing the outdated single-storey MRI scanner building, providing Milton Keynes with a cutting-edge medical facility.

Construction is taking place in an active hospital setting on a logistically tight site footprint, ensuring safe pedestrian and public movement at all times.

We commenced on site in August 2024, beginning demolition of the existing building in October, and are due to handover the newly completed 2-storey building in March 2026.

Site Activities

We’ve successfully completed all concrete slab pours, marking a major structural achievement for the project. We have begun striking the propping, so we can really see the building beginning to take shape!

We have also successfully completed the medical gas supply through the existing hospital, to link to both the new Imaging Centre and Oak Wards.

Upcoming work

May ramps up with several new trades starting on the project.

External envelope works will begin with the SFS installation around the building perimeter, followed by low level brickwork at the end of the month.

Internally, damper installation will get underway in the roof plantroom as part of the mechanical services fitout.

An EGGciting time

Morgan Sindall and our supply chain supplied over 100 Chocolate eggs to the Children’s Ward at MKUH.

A big thank you to our supply chain for supporting this cause:

  • T Clarke (MEPH)
  • Munro Services (MEPH)
  • Oliver Connells & Son (Groundwork and Frame Construction)
  • TJ Electrical (Site Temporary Services)
  • SCL Interiors (Drylining)

Keep revisiting the project microsite for more regular updates!